Project Snapshot

On the 2025 construction of 40 factories in Sudair Industrial City, TECHNO Soil Lab's scope covered geotechnical boreholes, backfill compaction, concrete-pour monitoring, and construction quality testing. The case shows soil and concrete testing coordinated within one program across multiple industrial work fronts.

Scope of Work

A Full Work Cycle for a Large-Scale Industrial Project

The recorded scope links three stages: soil boreholes during foundation investigation, backfill-compaction work, then concrete-pour monitoring and quality testing during construction. With 40 factories involved, identifying each visit location, test type, and work stage was central to coordinating the laboratory program with Labanat Al-Bena Contracting and Al-Jasarah Project Management.

The Role of Soil Boreholes in the Quality Program

The soil-testing contribution began with the geotechnical boreholes recorded in the project scope, followed by backfill and concrete monitoring. This sequence distinguishes pre-foundation ground investigation from construction quality-control tests: each stage answers a different engineering question and produces a separate project record.

Project Gallery

40-Factory Construction - Sudair Industrial City

Related Articles

Related Projects

Have a project underway?

Talk to our field team about testing and quality assurance for your build.

Start your project with us