Laboratory Service

Asphalt Testing Laboratory: Density & Compaction in Qassim

Asphalt mixture and pavement testing covering Marshall, binder content, gradation, Gmm, cores, thickness, density, and compaction to project specifications.

Asphalt Testing Laboratory: Density & Compaction

Asphalt Testing in Qassim

Qassim (Al-Qassim) roads connect separated towns and carry farm and truck traffic through an inland climate with intense summer heat. Rutting, texture loss, or cracking can have several causes, so weather alone is not a diagnosis. Every sample needs a link to its mix, layer, location, construction history, and drainage setting.

Production material and road cores

Mix work may include Marshall stability and flow, binder extraction, aggregate grading, and maximum theoretical specific gravity. After paving, planned cores can provide visible thickness and bulk density for compaction against the project reference. Reports retain road, lane, station, and date, applying the specified ASTM, SASO, or contract method without assuming a universal limit.

Distance shapes the sampling window

Our Qassim field team covers work near Al Rass, Al Khabra, Ad Dulaymiyah, An Nabhaniyah, and Dulay Rashid. On normal days, typical arrival starts at 5–20 minutes within Al Rass, while far towns are listed at 70–120 minutes. Paving or cutting time should be coordinated before travel.

  • Provide the JMF, layer, and density reference.
  • Map lane, direction, and stations.
  • Arrange cutting permission and traffic protection.
  • Confirm core-hole reinstatement.

For existing distress, photograph its limits first and connect observations to each core number. This keeps the investigation tied to the actual section of a long inter-town road.

Areas We Cover in Qassim

Our Qassim field team covers 15 towns and municipalities across five groups around Al Rass. Listed times are typical on normal days and may vary with roads, entry clearance, and site readiness.

Al Rass

≈ 5–20 min
1 districts · Show districts

Al Rass

Towns near Al Rass

≈ 25–45 min
4 districts · Show districts

Al Badayea, Al Khabra, Riyadh Al Khabra, Qasr Bin Aqil

Mid-range towns

≈ 40–70 min
4 districts · Show districts

Al Bukayriyah, Ad Dulaymiyah, An Nabhaniyah, Dukhnah

Far towns

≈ 70–120 min
4 districts · Show districts

Al Quwarah, Al Fuwarah, Az Zahiriyah, Dulay Rashid

Outer region

≈ 90–160 min
2 districts · Show districts

Uqlat As Suqur, Dariyah

Estimated driving times from the lab on normal days; they can be longer during Ramadan and the Hajj season.

In Short

Asphalt testing is a field and laboratory service for asphalt mixtures and paved layers; it is not asphalt supply or paving-equipment rental. Scope can include Marshall, bitumen content and gradation, maximum theoretical specific gravity, asphalt cores, thickness, density, and compaction. Results are compared with the project specification and approved JMF.

Asphalt Testing Laboratory for Pavement Quality

Asphalt quality control connects three stages: source materials, the produced mixture, and the layer after placement and compaction. The JMF records the target composition and limits. Production samples and cores then show whether the tested mixture and paved layer align with the requirements supplied to the laboratory.

Asphalt density alone is not enough to evaluate paving. The reference density, calculation method, core location, layer thickness, and mixture results all matter. The laboratory reports measurements and comparisons, while the authorized project party determines acceptance or corrective action under the contract and specification.

Link each mixture sample or core to its location, layer, and paving date
Clearly separate mix-design, production-control, and paved-layer results
Calculate compaction using the project-specified reference and method
Flag results needing review against the JMF or specification limits

Asphalt Mixture and Post-Paving Core Tests

The test package follows the project stage and the question the results must answer.

Laboratory Mixture Samples

Testing mix components or production samples against the target mixture.

Marshall stability and flow where specified
Bitumen extraction and gradation of recovered aggregate
Maximum theoretical specific gravity (Gmm) for void or compaction calculations
Binder or aggregate tests when included in the quality plan

Field and Paved Layer

Sampling or coring with location records, followed by paved-layer measurements.

Asphalt cores from locations defined by the inspection plan
Thickness of the layer or visible layers in the core
Bulk density of the compacted specimen
Compaction percentage against the project-specified reference density

Common Asphalt Testing Standards

The governing method, limits, and frequency come from the approved project documents.

ASTM D6926 / D6927

Marshall specimen preparation and stability and flow testing

ASTM D2172/D2172M

Quantitative extraction of asphalt binder from mixtures

ASTM D5444

Sieve analysis of extracted aggregate

ASTM D2041/D2041M

Maximum theoretical specific gravity of asphalt mixtures (Gmm)

ASTM D5361/D5361M

Sampling compacted asphalt mixtures

ASTM D2726/D2726M

Bulk specific gravity of non-absorptive compacted specimens

ASTM D3549/D3549M

Thickness measurement of compacted asphalt specimens

From the JMF to Asphalt Density and Compaction Results

Every sample should trace to the mix, layer, location, and comparison reference.

1

1. Review Scope and References

We collect the project specification, JMF, layer type, sampling locations or frequency, and required tests.

2

2. Sample and Record

The mixture sample or core is identified by date, location, orientation, and layer, with condition recorded on receipt.

3

3. Test and Calculate

Agreed tests are performed and density or compaction is calculated using the specified reference rather than an assumed generic value.

4

4. Report and Compare

The report presents methods, results, location data, and the supplied JMF or specification limits, highlighting items needing review.

Included Tests

10 field and laboratory tests available by project scope

Prime Coat Spray Rate (MC1)

معدل رش الطبقة التشريبية (MC1)

Unit: test

Tack Coat Spray Rate (RC2)

معدل رش الطبقة اللاصقة (RC2)

Unit: test

Bitumen Content in asphalt mix

نسبة البيتومين في الخلطة الإسفلتية

ASTM D2172

Unit: sample

Gradation of asphalt sample

التدرج الحبيبي للأسفلت

ASTM D2172

Unit: sample

Maximum Theoretical Specific Gravity (Gmm)

أقصى كثافة نوعية نظرية (Gmm)

ASTM D2041

Unit: sample

Marshall Stability & Flow (6 molds)

الثبات والفاقد — مارشال (6 قوالب)

ASTM D6926 / D6927

Unit: sample

Flash Point (bitumen)

نقطة التوهج (البيتومين)

Unit: sample

Viscosity Coefficient (bitumen)

معامل اللزوجة (البيتومين)

Unit: sample

JMF Quality Control (Coarse Agg, Fine Agg, Filler, MC1)

مراقبة جودة مكونات الخلطة (JMF)

Unit: test

Asphalt Core Sampling (with report)

كور أسفلتي (مع تقرير)

Unit: sample

Equipment used for this service

Why Choose Us

Why TECHNO Soil Lab?

10
Available Tests

Field and laboratory tests selected to match the project scope

15+
Years Experience

Accumulated technical experience in testing & engineering consultancy

5
Cities Served

Head office in Makkah, with equipped field teams in all five cities

The complete Asphalt Testing Laboratory: Density & Compaction guide

Test selection by project type, the pre-contract checklist, what drives the quote and what the report contains — on the main service page.

Read the full guide

Projects Where We Ran This Service

Related Reading

Common Questions

FAQ About Asphalt Testing Laboratory: Density & Compaction

On normal days, typical arrival starts at 5–20 minutes within Al Rass, then 25–45 minutes for nearby towns, and reaches 90–160 minutes for the outer region. These estimates vary with roads, entry clearance, and site readiness.

Other Services You May Need

Explore the rest of our accredited engineering tests in one place

Need Asphalt Testing Laboratory: Density & Compaction Services?

Our specialized team is ready to mobilize to your site anywhere in the Kingdom.