Concrete Testing Laboratory: Site & Lab Tests in Makkah

Fresh and hardened concrete testing covering slump, temperature, specimens, compressive strength, concrete cores, and non-destructive methods to project specifications.

Concrete Testing Laboratory: Site & Lab Tests

Concrete Testing in Makkah

Concrete sampling works best when the visit is booked before the first truck is dispatched. Hot summers in Makkah (Mecca) can make workability change quickly during hauling and site queues, so the pour time, structural element, sampling matrix, and specimen protection need to be clear in advance. Testing documents the sampled concrete; it does not replace site supervision or curing control.

Fresh and hardened concrete checks

For a scheduled pour, the technician can sample fresh concrete, measure slump and temperature, and record the truck, element, and sampling time. Air content or unit weight can be included when requested. Cubes or cylinders are then identified, transported, cured, and tested for compressive strength at the project-specified ages. Existing concrete may call for cores, Schmidt hammer readings, ultrasonic pulse velocity, permeability, absorption, or chloride testing under a defined investigation plan.

Scheduling across the city

Our team travels from Al-Bay'ah in Ash-Shara'i. Typical normal-day driving is about 20 minutes to Al-Aziziyah, 30 minutes to Ajyad or Al-Ghazzah, and 32 minutes to Al-Utaybiyah. Hajj and Umrah traffic may require an earlier dispatch and a confirmed meeting point.

Send the pour pin, start time, site contact, element, design requirement, specimen count, test ages, and governing ASTM, SASO, or project method. At sites in Al-Awali, An-Naseem, or Az-Zahir, reserve a level shaded area where specimens can be made, labelled, and protected from movement.

Areas We Cover in Makkah

Our field teams set out from the lab in Al-Bay'ah, Ash-Shara'i, to all ten sub-municipalities of Makkah (Mecca) — 101 districts under the official names adopted by the Makkah Municipality.

Ash-Shara'i

≈ 12 min

Lab HQ

21 districts · Show districts

Ath-Thaniyah, Zamzam, Uhud, Al-Maqam, Ash-Shara'i, Al-Yamamah, At-Tarwiyah, As-Salam, Ar-Rashidiyah, Al-Kawthar, Al-Mughammis, Ma'ad, Al-Khadra, Al-Bay'ah, Al-Marwah, As-Sanabil, Al-Barakah, Taybah, Al-Fath, Al-Abidiyah, Al-Ji'ranah

Al-Aziziyah

≈ 20 min
10 districts · Show districts

Al-Aziziyah, Al-Jami'ah, Al-Mursalat, Al-Awali, An-Naseem, Al-Husayniyah, Badr, As-Safa, Tuwa, Al-Hudaybiyah

Al-Ma'abidah

≈ 27 min
9 districts · Show districts

Al-Jumayzah, Al-Khansa, Ar-Rawdah, As-Sulaymaniyah, Al-Adl, Al-Ma'abidah, Jabal An-Nur, Wadi Jalil, Ri' Adhakhir

Al-Masfalah

≈ 27 min
7 districts · Show districts

Al-Masfalah, Kudai, Ar-Rusayfah, At-Taqwa, Al-Hindawiyah, Jurhum, Al-Khalidiyah

Ajyad

≈ 30 min
2 districts · Show districts

Ajyad, Al-Hatim

Al-Ghazzah

≈ 30 min
6 districts · Show districts

Rua Al-Haram, Jarwal, Al-Hajun, Al-Biban, At-Taysir, Hunayn

Al-Umrah

≈ 30 min
12 districts · Show districts

An-Nawariyah, Al-Umrah, At-Tan'eem, Al-Buhayrat, Dar As-Salam, Qurtubah, Al-Hamra, Umm Al-Jud, Ash-Shumaysi, Al-Usaylah, Al-Aqabah, Ar-Rawabi

Al-Utaybiyah

≈ 32 min
8 districts · Show districts

Al-Andalus, Al-Utaybiyah, Ash-Shuhada, Az-Zahra, An-Nuzhah, Ad-Diyafah, Az-Zahir, As-Salamah

South Makkah

≈ 35 min
15 districts · Show districts

Haret Al-Bab (New), Ash-Shubaykah (New), Ash-Shamiyah (New), Shi'b Amir (New), Shi'b Ali (New), Al-Judariyah (New), Al-Hajlah (New), Al-Misyal (New), As-Suq As-Saghir (New), Al-Qashashiyah (New), Al-Ghazzah (New), Al-Qararah (New), Al-Mudda'a (New), Al-Falaq (New), An-Naqa (New)

Ash-Shawqiyah

≈ 35 min
11 districts · Show districts

Al-Hijrah, Ash-Shawqiyah, Al-Kakiyah, Al-Ukayshiyah, King Fahd, As-Safwah, Al-Muhammadiyah, Al-Furqan, Al-Basatin, As-Safrah, Batha Quraysh

Estimated driving times from the lab on normal days; they can be longer during Ramadan and the Hajj season.

In Short

A concrete testing laboratory evaluates fresh concrete on site and hardened concrete in the laboratory or an existing structure. The scope can include sampling, slump and temperature, compressive strength, concrete cores, and non-destructive tests. Test frequency, specimen quantity, ages, and acceptance criteria follow the project specification and approved inspection plan.

Concrete Testing Laboratory for Site and Lab Work

Concrete testing does not begin at specimen crushing. A useful result depends on representative sampling, recording the pour and element location, preparing and curing specimens, and applying the specified test method. We connect field records, specimen identification, and laboratory results in one traceable workflow.

The service supports pour monitoring, compressive-strength verification, and post-pour investigation when a result needs review or an existing structure is being assessed. The laboratory does not independently accept or reject a structural element; results are compared with the design requirement and project specification for the engineer or consultant to evaluate.

Link each specimen to its pour date, element, and sampling location
Clearly separate field observations from specimen or core strength results
Flag results that need review against the stated project requirement
Add durability or non-destructive tests when the project scope requires them

Fresh and Hardened Concrete Testing Scope

We define the test matrix from the project specification and concrete condition instead of applying one package to every project.

On Site During the Pour

Fresh-concrete checks and specimen records before laboratory transfer.

Sampling according to the inspection plan or project instruction
Concrete slump and temperature testing
Air content or unit weight when requested
Recording the pour, element, truck, and sampling time

In the Lab or Existing Structure

Hardened-specimen tests or post-pour investigation for the defined purpose.

Compressive-strength testing at project-specified ages
Concrete core sampling and testing when approved in the investigation plan
Schmidt hammer and ultrasonic pulse velocity as non-destructive tests
Permeability, absorption, and chloride tests where included in scope

Common Concrete Testing Standards

The governing method, sampling frequency, and acceptance criteria come from the approved project documents.

ASTM C31/C31M

Making and curing concrete test specimens in the field

ASTM C143/C143M

Slump testing of fresh concrete

ASTM C39/C39M

Compressive strength of cylindrical concrete specimens

ASTM C42/C42M

Obtaining and testing drilled cores from existing structures

ASTM C805/C805M

Rebound number of hardened concrete using a Schmidt hammer

ASTM C597

Ultrasonic pulse velocity through concrete

ASTM C1202

Electrical indication of resistance to chloride ion penetration

How We Coordinate Concrete Pour Testing

The schedule, visit count, and specimen matrix are confirmed in the scope before work starts.

1

1. Review Pour Requirements

We collect the site, pour window, structural element, design requirement, and inspection plan or consultant instruction.

2

2. Field Testing

The technician performs the agreed field tests, takes specimens, and records the pour and sampling details.

3

3. Transfer, Curing, and Testing

Specimens are transferred, cured, and tested at the specified ages while each specimen set remains identifiable.

4

4. Issue Results

The report presents specimen data, test method, results, and the recorded requirement, highlighting results that need technical review.

Included Tests

12 field and laboratory tests available by project scope

Pour supervision + temp/slump + cube sampling (7 & 28 day)

الإشراف على صب الخرسانة + هبوط + عينات مكعبات (7 و28 يوم)

ASTM C143 / C1064 / BS EN 12390-2/-3

Unit: sample

Air Content

محتوى الهواء

ASTM C231

Unit: test

Unit Weight

وزن الوحدة

ASTM C138

Unit: test

Initial & Final Setting Time

زمن الشك الابتدائي والنهائي

ASTM C403

Unit: test

Thermocouple Test (mass concrete)

مراقبة حرارة الخرسانة الكتلية (Thermocouple)

ACI 301 / ACI 207.1R

Unit: test

Bleeding of Fresh Concrete

نسبة النضح

ASTM C232

Unit: test

Concrete Core Samples (with report)

كور خرساني (مع تقرير)

ASTM C42

Unit: sample

Ferro Scan (rebar detection)

الكشف عن حديد التسليح (Ferro Scan)

Unit: point

Schmidt Rebound Hammer

مطرقة الارتداد شميدت

ASTM C805

Unit: point

Ultrasonic Pulse Velocity (UPVT)

الموجات فوق الصوتية (UPVT)

ASTM C597

Unit: test

Half Cell Potential (corrosion)

نسبة الصدأ في حديد التسليح

ASTM C876

Unit: test

Concrete Durability Package (5 tests)

حزمة ديمومة الخرسانة (5 اختبارات)

BS 1881 / BS EN 12390-8 / ASTM C1202

Unit: sample

Equipment used for this service

Why Choose Us

Why TECHNO Soil Lab?

12
Available Tests

Field and laboratory tests selected to match the project scope

15+
Years Experience

Accumulated technical experience in testing & engineering consultancy

5
Cities Served

Head office in Makkah, with equipped field teams in all five cities

The complete Concrete Testing Laboratory: Site & Lab Tests guide

Test selection by project type, the pre-contract checklist, what drives the quote and what the report contains — on the main service page.

Read the full guide

Projects Where We Ran This Service

Related Reading

Common Questions

FAQ About Concrete Testing Laboratory: Site & Lab Tests

On normal days, typical driving is about 20 minutes to Al-Aziziyah, 30 minutes to Ajyad or Al-Ghazzah, and 32 minutes to Al-Utaybiyah from Al-Bay'ah. Book before the pour because traffic, schedule changes, and pilgrimage seasons affect arrival.

Other Services You May Need

Explore the rest of our accredited engineering tests in one place

Need Concrete Testing Laboratory: Site & Lab Tests Services?

Our specialized team is ready to mobilize to your site anywhere in the Kingdom.